Institutional construction — school
CODE School, Skardu
Project overview
A school project on the Katpana desert floor near Skardu, in Gilgit-Baltistan. Construction so far covers site formation and the perimeter: shifting and levelling sand ground with wheel loaders and tractors, building a stone masonry plinth to found on, and raising concrete block boundary walls around the campus footprint. The building itself is fully designed — the renders here show the finished elevation and the interiors it is being built towards, including teaching spaces, administration offices and a fitness room.
Scope delivered
- Clearance and levelling of open desert ground
- Bulk earthworks with wheel loaders and tractor haulage
- Stone masonry plinth and retaining courses
- Concrete block perimeter walls to the campus boundary
- Setting out of the building footprints
Key materials and features
This site is the opposite of a city job in almost every respect. It sits at altitude on loose sand, a long way from the nearest supplier, with a short working season and materials that have to be brought in rather than ordered locally. Stone is quarried and laid on site for the plinth and retaining work, which is both the practical and the economical answer that far from a block plant.